ABSTRACT
Panchayat Raj& Rund Davelopment Department - Reforms in Panhayati Raj Engineering Department - Revision and streamlining of Tender Procedure - Orders- issued
2. G.O.Ms.No.177 to 182, I& CAD (PW:COD) Department, dt.27-9-97
3. G.O.Ms.No. 477, PR & RD (Proga-II) Dept, dt.12-11-6B
4. G.O.Ms.No.94, PR & RD (Estt-III) Dept, dł.B-3-99
5. G.O.Ms.No.95, PR & RD (Estt-III) Dept, 0I.8-3-90
6. G.O.Ms.No. 23, I & CAD (PW.COD) Dept, dt.5.3.80
7. From the Engineer-in-Chief(PR) Letter NO.T1/10744/05, dated 6.4.99
Government have from time to time initiated several reforms in tendering for Public works with a view to bring in simplification of procedures, greater transparency and to ensure better quality of works.
2. Government issued orders in the G.O 2ndread above introducing comprehensive reforms streamlining and standardising the procedures for calling tenders and award of contracts.
3. Government issued ordars in the G.O. 3rd read above, ordering further tender reforms with a view to curb collusion and unfair practicess adopted by the Contractors in the tendering process.
4. Aftar isauance of the aforesaid orders, cornplaints were received by the Government that the Contractors were still indulglng in unfair practices and colluding in filing the tenders. Government, therefore, with a view to take stringent action in such cases, convened a workshop on 10-11-1996, with the representatives of Builders Association, Contractors and Government Officials to elicit their vieves on furthar reforms required to be introduced. The Committee constituted with the represantatives of the Builders Association and Government Officials, after thorough examination of the consensus emerged in the workshop has made certain recommendations to Govemment.
5. Government after carefull consideration of the recommendations of the Cabinet Sub Committee and in partial modifications of the orders issued in G.O.Me.No, 477, PR & RD Department, dt.12-11-1998, issue the following orders in respect of Tender procedures and othar allied matters relating to Panchayati Raj and Rural Development Department to ensure free and fair competition in award of Works and to bring in greatar transparency in tender procedure.
- Individual PWS Schemes in a Mandal or Assembly Constituency shall be packaged into viable financial units of say Re.100.00 lakhs and above. The packages shall be tendered and entrusted to experienced Registered contractors on turn key system, i.e. construction, testing, commissioning and maintenance of the scheme for 2 years and all materials like Steel, Cement, Pipes, Pumps, Specials and Motors etc, required for the work shall be procured by the contractors only and department shall not procure any material. Payment shell be made on the basis of finished work.
- The maximum ceillng of excess tender percentage shall be 15% instead of 20% allowad earlier. The lower limit and the conditions therefore will be continued. No negotiation will be conducted with the tenderers. Tender received with more than 15% excess shall be summarily rejected.
- In order to maintain anonymity, tender schedulls shall be supplied on payment of a cost to any contractor in tendering. The present practice of collecting EMD at the time of sale of Tender Schedules shall be dispensed with. Here after, the Contractors shall pay the EMD at the time of filing their tender documents only. The EMD shall be at the rate of 1% of estimated contract value and it shall be paid in full, wñhout concession, either in the shape of a Bank Demand Draft or unconditional Bank Guarantee.
- For the works costing upto Ra.10.00 lakhs. The eligibility criteria i.e., financial and physical shall not be made applicable for these works.
- The Contractors will no longer be required from now onwards to produce clearance cartificate from the Mines Department and Seigniorage charges wlll be deducted by th concerned works Departmant from the bills of the Contractors for the materials used on the works.
- The Contractors will be allowed the facility of deductton of sales tax at the rate of 2% at source and be exempted from producing the clearance certificate from Commercial Tax Department.
- Expert Committees at different levels shall be constituted by Departments to resolve the disputes of the Contractors in so far as technical issues are concerned.
- To resolve the problems of the Contractors vis-a-vis the Government, an institutional mechanism will be created at the district leval with the Collector as the Chairman and at the State level the Chief Secretary as Chairman to reviaw periodically and to redress the difficulties of the Contractors.
- To enforce quality control standards in execution of the performance of the Contractors and the Engineers incharge of the work shall be graded by Associating professional bodies and suitable incentives / punitive system shall be impliamented on the basis of such grading ard stern action will be taken for defective works against both the Engineers as well as Contractors.
- Quality control shall hereafter be the primary responsibility of the Engineers executing the Works.
- As a measure to encourage good contractors, the procedure of registration shall be rationalised and made more scientifc by introducing a grading syatem, which will take into account the technical qualification of the contractors, their standing in the civil contract fields, post track record of execution of works, ownership of plant and machinery, financial status and training, and memberships in professional bodies. The contractors with history of litigation will be suitably down graded/ black listed or debarred.
- Minor Irrigation works shall be entrusted to Ayacutdar committees as per guidelines issued tn G.O.RT. No. 1863, PR & RD (Prog-I) Department, Dated 23-11-98.
6. In order to avoid ambiguity in implementing tne order, datailed guidelines are formulated in Annexures I and II to this order.
7. The above orders shall come in to force with immediate effect. Howevar these ordars shall ba made applicable only for the tenders invited after isauance of the G.O
8. The Engineer-in-chief, PR Department shall furnish necessary proposals for making suitable amendmants to the G.O. 1st cited.
9. This order isued with the concurrance of Fin Plg(FW.EBS.XV) Department vide their U.0.No 17789/223/EBS.XV/A1/99, dated 23.4.1099.
The Engineer-in-Ceief, Panchayati Raj, Hyderabad.
All Chief Engineers, Panchayat Raj Engineering Depanment
Tha Commissioner, Panchayati Raj& Rural Devalopment
All Chief Executive Officers of all Zila Parishads
Copy to All Superintending Engineers PR & RWS.in the State. The Accountant General, Andhra Pradesh, Hyderabad Finance & Planning (Fin EBS XV} Department.
I & CAD department
TR &B Department.
PR & RD (RWS.II/ Mandal-I) Dept.
P.S. to Ministor (PR & RD)
P.S. to Principal Secretary to Government, PR & RD
P.S. to Principei Secretary to Government,(RD), (PR & RD)
S.F.
Panchayat Raj Department
Offlce of tha Engineer-in- Chief (PR) Hyderabad
Endt.No.T1/29042/96 dated: 14.05-1999
Communicated in continuation of this office circuar Memo No TI/29042Ø6, dt30-3-99. with a request to follow the Government order scrupulously and communicate this G.O. upto to level of Deputy Executive Engineer(PR) under their jurisdiction.
G.0.Ms.No.195 PR & RD (Progs-II)Dept, dated 10.5.99
- The standard data which folia basis for preparation of estimates for all Civll Engineering Works shall be updated taking the improved Construction technology in to consideration.
- The Chairman, Board of Chief Engineers and Engineer-in-Chief (Admin) I &CAD Department shall complete the updation of standard data with in a period of six months
- The SSRs shall be finalised bafore June without exception every year. The preparation of SSR shall be made more transparent by associating the representatives of Construction Industry, National Academy of Constructicn and the Institution of Engineers (India) A. P. State Centre, at the time of finalisation. For cities like Hyderabad and Vitakhapatnam. Unit rates will be prepared for various component items.
In order to prepare realistic estimates, the following provisions are permitted to be addad in the estimate.
- Turnover tax at the rate of 1 percent for item relating to canal digging lining, repairing road works etc., where the earth work excavation and embankment is involved and for works other than the above, turnover tax at 3 percent shall be added in the data.
- A Lumpsum provision shall be made in the abstract estimate towards works, by obtaining details of Insurance premium from Insurance.
- A lumps-um provisions shall be made in abstract estimates to meet tha expenditure to be incurred by the Contractor on engaging Technical Personnel based on number of persons indicated in the tender document and permissible wages as per SSRs.
- A lumpsum provisions shall be made in the abstract estimate towards Banker&pos;s charges for obtaining Bank guarantees for payment of E.M.D., performance security and release of retention amount as per prevailing procedure based on the period i.e. period of completion plus defect liability period. The Chief Engineer concerned shall assess duly obtaining the details there of from the Scheduled Banks and suitable provision shall be made.
- A provision at 1 percent of the cost of Cement towards construction of temporary store shed shall be added on the data of relavant items.
- Stripping where the depth is inadequete for handling with machinary
- Excavation of sub-minor and field channels, narrow reaches and formation of Sub-grade base for receiving lining of canals, excavation of rock toe, toe drains, filter drains and building foundations and Pipe line trenches.
- Detailad investigation
- Preparation of detailed designs/drawings
| AE/AEE | 25,000 |
| Dy.E.E. | Upto Rs.2,0D,000/- |
| E.E. | Above Ra.2.00 lakhs to Re.10.00 lakhs |
| S.E. | Above Rs. 10.00 Lakhs to Rs.50.00 Lakhs |
| C.E. | Above Ra. 50.00 Lakhs |
- To qualify for award of the Contract, each bidder, in his/ her name should have, during the last five years (specified financial years i.e. they should be immediately preceding the financial year in which tenders are invited)
- Satisfactorily completed not less than 90 percent of contract value as a prime contractor and similar works of value not less than Rs. @ (usually not less than 50% of estimated value of contract) in eny one year, during the tast 5 years.
- Should hava executed in any one year, the following minimUm quantities of works.
Cement concrete including RCC and PSC Cu. M Earth work in both excavation and embankment Cu. M OHSRs Nos and total capacity in liters Pipeline laying, joiming & testing Km Filters Units Ltrs a) Rapid Sand Filters b)Slow Sand Filter Supply erection and testing of power pumps K.W (Relevant principle items be indicated) (Usually 50 percent of the expected peak quantities of construction per year) - Each bidder should further demonstrate
- Availability either owned or leased of the followlng key and critical equipment for the work
- Road Rollers (8 to 10 T )
- Water Tanker
- Proclainers
- Concrete Mixtures
- Pipe Line hydraulic testing equipment
- Equipment for BT work with cold Mix
- Equipment for BT work with hot mix
- Availability of the Key personnel with adequate experience as required should be indicated based on the requiremennt for that work to be executed.
- Liquid asetts/ credit facilities of not less than Rs.______________lakhs(credit lines letter of ered / solvency certificate from Banks etc., shall be equivevalent of the estimated cash flow for three months in peak
- EMD in the shape of Bank Guarantee in the standard format enclosed, for Rs.(one percent of the estimated contract value) to be valid for the period as indicated at para (d) i.e. pariod of completion plus defect liability period.
- Experience relating to the works executed in State/ Central Government departments or State/ Central Government undertaktngs shall only be considered.
Where
A= Maximum value of civil engineering works executed in any one yaer dunng thę last five years (updated_______________________ price lavel) taking into account the completed as well as works in progress.
N= Number of years prescribed for, completion of the works for which tenders are invited. If months are specified they shall be converted in to years
B= Value of existing comitment and ongoing works to be completed during the period of completion of works for which tenders are invited
Note:-The statement showing the value of existing commitments and ongoing works as well the stipulated period of completion remaining for each of the works listed should be issued by the Engineer-in-Charge of Government department, not below the rank of Executive Engineer or equivalent and countersigned by Superintending Engineer or equivalent. The statement to the above effect shall be clearly enclosed to the Bidding Document, and the tenderer shall furnish the perticulars invariably in the same format failing which the tender shall be treated as incomplete and summarily be rejected.
*The financial year in which bids are invited.
The EMD wfll be returned to the qualified but unsuccessful tenderer either after finalisation of tenders or on expiry of validity of tendee which evor earlior