Menu

Requested to Donate, to receive required documents through e-mail. To donate click Pay Now Follow to receive updates by email.

Thursday, August 6, 2020

G.O.Ms.No.10 entrust of P.R. Works without Rice

GOVERNMENT OF ANDHRA PRADESH
ABSTRACT

Panchayat Raj and Rural Development- Reforms in Panchayat Raj execution of works with rice tied up with rice component- Method of entrustment of works- Certain guuidelines- Orders Issued.
-----------------------------------------------------------------------------------------------------------------------------------------------
PANCHAYAT RAJ AND RURAL DEVELOPMENT (PROGRESS-1A) DEPARTMENT
G.O.Ms.No. 10.
Dated 10th January, 2006.

Read the following :-

  1. G.O.Ms.No.37, P.R.&RD (progress-1A) Dept., dt 18-2-2005
  2. G.O.Ms.NO 198, P.R.&RD (RWS-1) Dept., dt 06-6-2005.
  3. G.O.Ms.No.18, Planning(V-1) Dept., dt 09-11-2005.
  4. From the Chief Engineer Panchayat Raj, Hyderabad Lr.No.W/19/4555/PKM/2005, dated 18-11-2005.
  5. From the Engineer in Chief, Panchayat Raj, Hyderabad. Lr.No.T1/18233/75. ted 19-12-2005.

*****

ORDER:

1).  In the reference 1st read above,orders were issued entrusting the works with an upper limits of Rs. 5-00 lakhs, to th works committees, Sef Hlf Goups at village level with certain guidelins.

2) In the reference 2nd read above, orders were also issued extending the scope of orders issued G.O. 1st read above, to the R.W.S. works on nomication basis costing up to Rs. 5-00 lakhs Rupees without tie rice up.

3). In the reference 3rd read above, orders were issued for execution of works under developmental proggrammes at the Assembly Constituancy level, with an upper limits of Rs. 5-00 lakhs can also be entrusted to village level works committee/ Self Groups/ User Groups consisting of stake holders. The nominee of the committee or group should enter in to an aggreement with the executine agency.

4). In the reference 4th and 5th read above, the Ingineer in Chief/ Chief Engineer Panchayat Raj, Hyderabad has requested to extend the powers of entrustment of P.R. works also on nomination basis costing the works up to 5-00 lakhs even without rice tie up as issued in G.O. 2nd read above, since there is descripancy P.R and R.W.S works in method of entrustment of works tied up rice component works and also non-availibility of rice in some of Districts.

5). Government of after carefull consideration of the mater, here by extend the power for entrustment of works with an upper limit of Rs. 5-00 lakhs even without rice tie up to the works committee/ Self Help Groups at the village level by following guidelines issued in the G.O. 1st read above.

6).  The Engineer in Chief Panchayati Raj, Hyderabad shall take necessary further action, in the matter, accordingly.


(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
M.SAMUEL.,
PRINCIPAL SECRETARY TO GOVERNMENT


1 comment:

Featured Post

Payment of Environment Impact fee

GOVERNMENT OF TELANGANA ABSTRACT Mines & Minerals - Payment of Environment Impact Fee @ Rs.3/- per Square feet for buildings abo...

Popular Posts