Works- e-Procurement- Invitation of bids through e-procurement for the works / supplies costing Rs. 1.00 Lakh and above- Uniformity in all the Departments- Orders -Issued.
From the DOWA, A.P., Hyderabad, Lr.No.DWA/HYD/SN.Il/A.9/2013-14/227, Dated.07-8-2013.
Minutes of the review meeting convened by the Chief Secretary to Government on 22-10-2013.
****
ORDER:
In the reference 4th cited, the Director of Works Accounts, Hyderabad has stated that different financial limits have been fixed by various departments for inviting bids through e- procurement platform as detailed below :
SI.No
Department
Items
Financial limit above which e-procurement is mandatory (Rs. In lakhs)
(1)
TR&B
Works
1.00
(2)
MA &UD
Works & Material
1.00
(3)
I &CAD
Works
5.00
2. The DOWA, therefore, requested that for all works and material procurement (for works and for stationery / livery supplies for offices etc. )costing Rs. 1.00 Lakh and above the platform should be adopted for enhancing transparency and also bringing uniformity across all the departments.
3. In the review meeting convened by the Chief Secretary to Govt. on 22-10-2013, the Chief Secretary desired that uniformity on adoption of c-Procurement has to be finalized within a month in consultation with the Board of Chief Engineers.
4. In view of the above, the Government, after careful examination, hereby issue orders that for all works and material procurement (for works and for stationery / livery supplies for offices etc.) costing Rs. 1.00 Lakh and above the c-procurement platform should be adopted so as to enhance transparency and bring uniformity across all the departments.
5. All the Special Chief Secretaries/Principal Secretaries/Secretaries of all Departments are requested to ensure strict implementation of the above instructions.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
Dr.P.K.MOHANTY
CHIEF SECRETARY TO GOVERNMENT
To
All Departments of Secretariat. Copy to:
Chief Secretary to Government
All Special Chief Secretaries / Principal Secretaries /
Secretaries of all Departments of Secretariat, All the District Collectors in the State.
Director of Works Accounts, Hyderabad.
SF / SC
P.R. & R.D. DEPARTMENT – Road and Bridge works – Adoption of overhead Charges and Contractors profit for Road and Bridge works taken up in P.R. & R.D. Department and allowing of tender premium in respect of works for which MORD specifications adopted – Permission – Accorded – Orders – Issued.
In the references 1st and 2nd read above TR&B Department have accorded permission adopting 20% overhead charges, contractors profit and allowing 5% tender premium in respect of works for which the Ministry of Road Transport and Highway (MORTH) specifications are adopted for all Road and Bridge works.
2. In the reference 3rd read above, the E-in-C(P.R.) has requested the Government to issue orders for adopting contractors profits, overhead charges, Tender premium to P.R. department also.
3. In the reference 5th read above orders were issued permitting 16.5% overhead charges for PMGSY Phase VI works which includes 10% contractors profit + overhead charges + 1.4% VAT subject to no tender premium of 5% normally permissible and no cost escalation.
4. During the review meeting it was pointed out that the different rates and different specifications within P.R. & R.D. Department and within P.R. & R&B Department are causing difficulties in eliciting the response from the contractor, which is resulting in slow progress of works. Therefore it has been proposed for all the tender works of Panchayat Raj department to follow the specifications of Ministry of Rural Development, Government of India which are by and large, same as manual specification of Ministry of Road Transport and Highway (MORTH). Apart from following a uniform specification of MORD to all the tender works in Panchayat Raj Department, it is proposed that the allowances given by R&B Department are also applicable to the works for P.R. Department including PMGSY. In case of Panchayat raj Department works the MORD standards shall apply with regards to specifications as well as use of machinery and the MORD rates are contigent to following of the standards as above.
5. Government have examined the matter carefully and hereby accord permission for adoption of 16.5% overhead charges which includes contractors profit at 10% for all the tender works of Panchayat Raj including PMGSY by following the specifications of MORD, subject to following conditions:
In framing data adopting MORD specifications, the component of overhead charge is included at the prescribed percentages. This component of overhead charges includes Sales Tax/VAT. Hence, this component of Sales Tax/VAT shall be deducted in the overhead charges in the data but, shall be separated and shown in Part-B of the estimate. The VAT component so deducted should not be less than the reimbursable amount.
A condition shall be included in the agreement that the VAT component loaded in the estimate shall be added in each bill of the contractors who opt for composition scheme and recovered.
In respect of those contractors, who do not opt for composition scheme, the VAT component loaded in the estimate shall not be released to them with their bills and VAT, however, shall be recovered and for the recovery made, a deduction certificate shall be issued, based on which they have to claim adjustment through their returns submitted to their respective assessing authorities.
6. Government hereby also order to allow 5% tender premium on par with TR&B Department in second or subsequent tender calls only.
7. The price escalation orders issued vide reference 4th read above are also applicable to all the tender works including PMGSY.
8. The above orders shall be implemented subject to the following conditions.
These orders are applicable with prospective effect only.
Already settled/closed cases shouldn’t be reopened for applying the orders of this G.O.
Price escalation clause should be allowed carefully duly ascertaining the fulfillment of all the aspects of quantity, quality and contractual obligations.
No cases of revised administrative sanction will be entertained.
The concession given under this G.O. are not applicable to the works entrusted on nomination basis.
9. This order issues with the concurrence of Finance (Expdr.P.R.& RD) Department vide their U.O.No.04947-A/88/A1/Expdr.P.R.& R.D./08,dt.19.2.2008.
10. The Engineer-in-Chief (P.R.) shall take necessary action accordingly.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
DR.V.P.JAUHARI
SPECIAL CHIEF SECRETARY TO GOVERNMENT
To
The Engineer-in-Chief(P.R.), Hyderabad.
Copy to:
Accountant General, A.P,,Hyderabad.
Finance (Expdr.P.R.) Department.
P.S. to M(P.R.)/Spl.C.S.
Sf/Sc.
PR&RD DEPT – Issues of Builders Association of India (AP Center) related to civil works in PR Department – Certain Guidelines - Orders – Issued.
*************************************************************
PANCHAYAT RAJ & RURAL DEVELOPMENT (PROGS.II) DEPARTMENT
G.O.Ms.No.23
Dated.11.02.2014
Read the following
G.O.Ms.No.1, Finance Dept (W&P), dt.25.2.2012
G.O.Ms.No.94, I&CAD (PW-COD) Dept, dt.1.7.2003
G.O.Ms.No.57 PR&RD (progs.II) Dept, dt.19.2.2008
Representation of Builders Association of India (AP Centre), dt.13.9.2012
Memo No.16274/Progs.II(1)/2013, dt.26.6.2013
From the ENC, PR Lr.No.T2/DEE-5/Builder’s Association/2013, dt.21.10.2013
***
ORDER:
In the ref 4th read above, Builders Association of India has submitted certain issues requesting to the Government to consider the same and issue suitable orders.
Price Escalation
Seinorage Charge
Tender Premium
VAT 5%
Labour Cess
Completion report
Over Head Charges
EOAT
Price Escalation Provisions
Tender Participation
Income Tax
Sand
Payment of Bills
2. In the ref 5th read above, Government has requested the Engineer-inChief, PR to examine and to furnish a detailed report on the representation of Builders Association of India. The ENC, PR has submitted a detailed report along with the minutes of Board of Chief Engineers held on 19.6.2013 and requested to take necessary action in the matter.
3. Government have convened a meeting on 17.10.2013 with the Engineer-in-Chief, PR/ Chief Engineers of PR Dept/ representative of Finance Dept/ Members of the Builders Association of Inida in the chambers of Hon’ble M(PR&RWS), the issues have been discussed as put-forth by the BAI in detail.
4. Government after careful consideration of the issues of the Builders
Association and hereby clarified on the following:-
i. Price Adjustment:-
Price Adjustment whether it is increase or decrease in the costs after deducting the basic 5%.
(contd---2)
::2::
As per G.O.Ms.No.1, Finance (Works&Projects-F-7) dept, dt.25.02.2012. Wherein Para-9 of the said G.O. is as follows:
“ Treatment of Price adjustment: It is observed that Departments are adopting diverse interpretations of the existing G.Os relating to treatment of price adjustment from 0 to 5%. After careful consideration, it has been decided that hence forth all the Departments should operate variation in rates only to the extent where it is above 5% over the estimated rates.
In context of the above, the price variation clause over and above 5% should be applied on either side (increase or decrese) and hence whenever there is decrease in price, recovery should be made from the contractor beyond 5% only similar to when there is increase in price
ii. Seignorage Charges:
The Executive-Engineer should ensure that the seignorage charges are deducted only once, and there should not be any double recovery towards seignorage charges while making payment to the contractor.
While scrutiny of bills before submission to PAO concerned, the EE should add the seignorage charges for arriving the value of the work done and propose for deduction the same for arriving the net amount payable to the contractor, and for adjusting the seignorage charges recovered thereby to the appropriate head by the PAO.
Provision towards Seinorage charges may be allowed in the estimates under Part-B
iii. VAT:-
As per U.O. Note. No. 2447, dt.17.08.12, Finance Department has informed to adopt VAT at 5% in place of 4% w.e.f 14.09.2011 for all ongoing and future works.
Government decided to allow provision towards VAT charges at 5% in the estimates under Part-B.
iv. Completion Report:-
Decided that the final payments to the contractors should be made as per approved work done estimate by the competent authority including part-B provisions, based on M. Book measurements after proper check of quantity and quality within a reasonable time limit. The final payment of the contractor should not be delayed for want of certificate from the quality control staff as already instructed in G.O.Ms.No.94, dt.1.7.2003 of I&CAD Dept. This is essential to discourage wanton delays, red tape and consequential ill practices in the department.
v. Over Head Charges:-
Government have decided to allow that the over head charges @ 14% and VAT @ 5% is being adopted as recommended in the AP Standard data for all the works in PR Dept except PMGSY works. For PMGSY works 12.5% over head charges and VAT 5% is being allowed as per MORD Specification.
(contd---3)
::3::
vi. Extension of Agreement Time:-
Decided to delegate the powers to the Engineer-in-Chief, Panchayat Raj for grant of EOAT without penalty up to 3 months in case where there are valid reasons such as Land Acquisition problems, delay in approval of designs, Court cases, obstruction of power lines and major natural calamities.
vii. Income Tax:-
As per the latest guidelines of the Income Tax Department, TDS rates and returns for the Assessment Year 201415(Financial Year 2013-14) where-in as per section 194 c (1) payment to Contractors on payment exceeding Rs.30,000/- for single payment is 1% to the individual and 2% for others.
5. The Engineer-in-Chief, Panchayat Raj /Chief Engineer, Panchayat Raj/Chief Engineer, Panchayat Raj NABARD/Chief Engineer Panchayat Raj, MGNREGS Hyderabad are requested to follow the above instructions with immediate effect.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
V.NAGI REDDY
PRINCIPAL SECRETARY TO GOVERNMENT
To
The Engineer in Chief, Panchayat Raj, Hyderabad
The Chief Engineer, Panchayat Raj, Hyderabad
The Chief Engineer, Panchayat Raj, NABARD, Hyderabad
The Chief Engineer, Panchayat Raj, MGNREGS, Hyderabad
All the Superintending Engineers (PR) in the State
Copy to
The Fin(Expr. PR&RD) Dept
The PS to M(PR&RWS)
The PS to Prl. Secretary to Govt.
Sf/Sc
Panchayat Raj& Rund Davelopment Department - Reforms in Panhayati Raj Engineering Department - Revision and streamlining of Tender Procedure - Orders- issued
Government have from time to time initiated several reforms in tendering for Public works with a view to bring in simplification of procedures, greater transparency and to ensure better quality of works.
2. Government issued orders in the G.O 2ndread above introducing comprehensive reforms streamlining and standardising the procedures for calling tenders and award of contracts.
3. Government issued ordars in the G.O. 3rd read above, ordering further tender reforms with a view to curb collusion and unfair practicess adopted by the Contractors in the tendering process.
4. Aftar isauance of the aforesaid orders, cornplaints were received by the Government that the Contractors were still indulglng in unfair practices and colluding in filing the tenders. Government, therefore, with a view to take stringent action in such cases, convened a workshop on 10-11-1996, with the representatives of Builders Association, Contractors and Government Officials to elicit their vieves on furthar reforms required to be introduced. The Committee constituted with the represantatives of the Builders Association and Government Officials, after thorough examination of the consensus emerged in the workshop has made certain recommendations to Govemment.
Contd.Page.2
Page.No.2
5. Government after carefull consideration of the recommendations of the Cabinet Sub Committee and in partial modifications of the orders issued in G.O.Me.No, 477, PR & RD Department, dt.12-11-1998, issue the following orders in respect of Tender procedures and othar allied matters relating to Panchayati Raj and Rural Development Department to ensure free and fair competition in award of Works and to bring in greatar transparency in tender procedure.
Individual PWS Schemes in a Mandal or Assembly Constituency shall be packaged into viable financial units of say Re.100.00 lakhs and above. The packages shall be tendered and entrusted to experienced Registered contractors on turn key system, i.e. construction, testing, commissioning and maintenance of the scheme for 2 years and all materials like Steel, Cement, Pipes, Pumps, Specials and Motors etc, required for the work shall be procured by the contractors only and department shall not procure any material. Payment shell be made on the basis of finished work.
The maximum ceillng of excess tender percentage shall be 15% instead of 20% allowad earlier. The lower limit and the conditions therefore will be continued. No negotiation will be conducted with the tenderers. Tender received with more than 15% excess shall be summarily rejected.
In order to maintain anonymity, tender schedulls shall be supplied on payment of a cost to any contractor in tendering. The present practice of collecting EMD at the time of sale of Tender Schedules shall be dispensed with. Here after, the Contractors shall pay the EMD at the time of filing their tender documents only. The EMD shall be at the rate of 1% of estimated contract value and it shall be paid in full, wñhout concession, either in the shape of a Bank Demand Draft or unconditional Bank Guarantee.
For the works costing upto Ra.10.00 lakhs. The eligibility criteria i.e., financial and physical shall not be made applicable for these works.
The Contractors will no longer be required from now onwards to produce clearance cartificate from the Mines Department and Seigniorage charges wlll be deducted by th concerned works Departmant from the bills of the Contractors for the materials used on the works.
The Contractors will be allowed the facility of deductton of sales tax at the rate of 2% at source and be exempted from producing the clearance certificate from Commercial Tax Department.
Expert Committees at different levels shall be constituted by Departments to resolve the disputes of the Contractors in so far as technical issues are concerned.
To resolve the problems of the Contractors vis-a-vis the Government, an institutional mechanism will be created at the district leval with the Collector as the Chairman and at the State level the Chief Secretary as Chairman to reviaw periodically and to redress the difficulties of the Contractors.
To enforce quality control standards in execution of the performance of the Contractors and the Engineers incharge of the work shall be graded by Associating professional bodies and suitable incentives / punitive system shall be impliamented on the basis of such grading ard stern action will be taken for defective works against both the Engineers as well as Contractors.
Quality control shall hereafter be the primary responsibility of the Engineers executing the Works.
As a measure to encourage good contractors, the procedure of registration shall be rationalised and made more scientifc by introducing a grading syatem, which will take into account the technical qualification of the contractors, their standing in the civil contract fields, post track record of execution of works, ownership of plant and machinery, financial status and training, and memberships in professional bodies. The contractors with history of litigation will be suitably down graded/ black listed or debarred.
Minor Irrigation works shall be entrusted to Ayacutdar committees as per guidelines issued tn G.O.RT. No. 1863, PR & RD (Prog-I) Department, Dated 23-11-98.
Contd.Page.3
Page.No.3
6. In order to avoid ambiguity in implementing tne order, datailed guidelines are formulated in Annexures I and II to this order.
7. The above orders shall come in to force with immediate effect. Howevar these ordars shall ba made applicable only for the tenders invited after isauance of the G.O
8. The Engineer-in-chief, PR Department shall furnish necessary proposals for making suitable amendmants to the G.O. 1st cited.
9. This order isued with the concurrance of Fin Plg(FW.EBS.XV) Department vide their U.0.No 17789/223/EBS.XV/A1/99, dated 23.4.1099.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
P.RAMAKAHTH REDDY
PRINCIPAL SEČRETARY TO GOVERNMENT(RD)
To, The Engineer-in-Ceief, Panchayati Raj, Hyderabad. All Chief Engineers, Panchayat Raj Engineering Depanment Tha Commissioner, Panchayati Raj& Rural Devalopment All Chief Executive Officers of all Zila Parishads Copy to All Superintending Engineers PR & RWS.in the State. The Accountant General, Andhra Pradesh, Hyderabad Finance & Planning (Fin EBS XV} Department. I & CAD department TR &B Department. PR & RD (RWS.II/ Mandal-I) Dept. P.S. to Ministor (PR & RD) P.S. to Principal Secretary to Government, PR & RD P.S. to Principei Secretary to Government,(RD), (PR & RD) S.F.
//Forwarded by Ordar//
Government of Andhra Pradesh Panchayat Raj Department Offlce of tha Engineer-in- Chief (PR) Hyderabad Endt.No.T1/29042/96 dated: 14.05-1999
Communicated in continuation of this office circuar Memo No TI/29042Ø6, dt30-3-99. with a request to follow the Government order scrupulously and communicate this G.O. upto to level of Deputy Executive Engineer(PR) under their jurisdiction.
The standard data which folia basis for preparation of estimates for all Civll Engineering Works shall be updated taking the improved Construction technology in to consideration.
The Chairman, Board of Chief Engineers and Engineer-in-Chief (Admin) I &CAD Department shall complete the updation of standard data with in a period of six months
1.02 Finalisatlon of Standard Schedule of Rates (SSR )
The SSRs shall be finalised bafore June without exception every year. The preparation of SSR shall be made more transparent by associating the representatives of Construction Industry, National Academy of Constructicn and the Institution of Engineers (India) A. P. State Centre, at the time of finalisation. For cities like Hyderabad and Vitakhapatnam. Unit rates will be prepared for various component items.
1.03. Provisons to be made in estimates
In order to prepare realistic estimates, the following provisions are permitted to be addad in the estimate.
Turnover tax at the rate of 1 percent for item relating to canal digging lining, repairing road works etc., where the earth work excavation and embankment is involved and for works other than the above, turnover tax at 3 percent shall be added in the data.
A Lumpsum provision shall be made in the abstract estimate towards works, by obtaining details of Insurance premium from Insurance.
A lumps-um provisions shall be made in abstract estimates to meet tha expenditure to be incurred by the Contractor on engaging Technical Personnel based on number of persons indicated in the tender document and permissible wages as per SSRs.
A lumpsum provisions shall be made in the abstract estimate towards Banker&pos;s charges for obtaining Bank guarantees for payment of E.M.D., performance security and release of retention amount as per prevailing procedure based on the period i.e. period of completion plus defect liability period. The Chief Engineer concerned shall assess duly obtaining the details there of from the Scheduled Banks and suitable provision shall be made.
A provision at 1 percent of the cost of Cement towards construction of temporary store shed shall be added on the data of relavant items.
Contd. Page. 5.
Page.No.5
1.04 At the time of preparation of estimates, proper care should be taken to provide the lumpsum provisions for the aforesaid items and necessary conditions also should be incorporated in the tender document for euitable reimbursement to the contractors from out of the above provisions, however not exceeding the amounts indicated against each, on production of the Insurance policies, copies of appointment orders with payments vouchers, Bank Guarantee etc. Failing to comply with the above, reimbursement shall not be allowed but suitable penalty shall be imposed for not engaging technical personnel and the Agreement authority shall take Insurance policy at the cost of contractor duly deducting the premium from the contractor’s bills. Contractor has to take policy in favour of the employer i.e. department.
1.05 For earth work excavation & embankment upto 10000 Cum. The manual rate shall be provided and if the quantity exceads 10000 Cum, the machinery rates shall be adopted. However, the contractor will be given an option either for manual or machine operations. For earthwork, quantity upto 10000 Cum, if the contractor executes not with machine operations, the machinery rates will be allowed. Irrespective of the quantities, the following items of works shall be taken up manually.
Stripping where the depth is inadequete for handling with machinary
Excavation of sub-minor and field channels, narrow reaches and formation of Sub-grade base for receiving lining of canals, excavation of rock toe, toe drains, filter drains and building foundations and Pipe line trenches.
2.0. Sanction of Estimates
2.01. Administrative Approval
Administrative approval to the estimates for works costing above Re. 50.00 lakhs or any bridge works or cause way and PWS schemes irreepective of Cost shall be given after fulfillment of following items.
Detailad investigation
Preparation of detailed designs/drawings
2.02 Technlcal sanction
The orders issued in G.0.Ms.No.94, PR & RD (Edit-III) Dapt, dt.8-3-99, are indicated below shall be applicable for according Technical Sanction to estimates.
AE/AEE
25,000
Dy.E.E.
Upto Rs.2,0D,000/-
E.E.
Above Ra.2.00 lakhs to Re.10.00 lakhs
S.E.
Above Rs. 10.00 Lakhs to Rs.50.00 Lakhs
C.E.
Above Ra. 50.00 Lakhs
The technical sanction shall be limited to the amount of administrative sanction/approval.
Contd. Page. 6.
Page.No.6
3.00. Preparation of tender documents and finalizatien of tenders
3.01 Tender documents
3.01.1 Tander Notice
The Tender notice or Notice inviting Tenders (NIT) will be approved by the Engineers for the works for which they are competent to accord technical sanction
The Tender documents will be prepared by the concerned Engineers, bringing greater transparency. Tha provisions made in the estimate for items which are reimbursable to the Contractors with conditions there for and other relevant conditions relating to the implementation of contract and other eilgibility criteria on both physical and financial requirements in addition to the conditions not withstandirng any thing contained in tha APSS, APWD code and government orders the following will be incorporated wherever necessary.
3.01.2. The defect liability
The defect liability period is increaeed to two years for the original works and one year for maintenance works, duly taking into account normal wear and tear.
3.01.3 Liquidated damages
The liquidated damages may be imposed on the present practice basing on the milestones.
3.01.4. Seigniorage charges & sales tax.
The seigniorage charges will be recovered from Contractor's bills as per the rates prescribed in the contract documents for the materials used on the work only. The present practice of insisting for production of documentary evidence for the having paid the seigniorage charges in interms of G.O.Ms.No.243 dated 8-5-86 and in the absence of such production of evidence, the imposition of five times penality is dispenced with.
For sales tax/tax on works contract, contractors are given an option to opt for the composing schemes under Section 5(g) of the APGST Act and those opting for it are subject to a tax deduction of 2% at source on the total value of tha contract irrespective of nature of work. In such case, tha departments wlll not insist on production of clearance certificate and no assessement of tax will be neaded. in case of contracts not opted for 2% tax deduction, Tax on works contract (Turn over tax) shall be recovered at the rates indicated in clause 1.03 (a) above.
3.01.5 Payment of bills
The contractors will be permitted to Submit their work bills once in a month and payment will be made after proper check of quantity and quality with in a reasonable time limit.
3.01.6. Quality Control Measures
Emphasis on the quality will be paramount. The concerned Departments are directed to strengthen the quality control mechinery of the Government by keeping a separate Chlef Englnaer for Quality control under the direct control of Government. The Chief Engineer, quality control should see that quality audit is done periodically and also evolve suitable punitive action against Contractors as well as Engineers in Charge of the Work who violate proper quality standards.
3.01.7. Construction matarials
The present practice that the contractor has to procure at his own cost the principal constructton materials like cement, steel, bituman, sand, metal and soils etc. shall continue
The present practice of procuring pipes, specials, valvee, pumps and Motors departmentally for execution of PWS Schemes is dispensed with. The contractors theem selves have to procure these materials with ISI mark where ever preecribed and will be responsible for supply, delivery, testing and commissioning of the scheme on turn key system and maintenance of the scheme for a period of (2) years. For all the materials, pre-delivery quality control inspection shall be done by Quality Control Wing of Panchayati Raj Department or Third party inspection as directed by the Engineer-In-Chief, Panchayat Raj. The inspection charges if done by third party, shall be born by the Contractor.
However, the payments shall be made based on finished work.
3.01.8 Earnest money deposit
In order to maintain the anonymity, Tender Schedules will be supplied on payment of cost to any contractor of eligible class interested in bidding, without insisting for EMD. This is introduced to enable prevention/ reduction of extraneous forcesinterefering or preassurising the contractors to quote or under quote or not to quote at all in the tenders. Hence the practice of collecting EMD in the shape of draft at the rate of 1.50 percent subject to a maximum of Rs.1.00 lakh or Rs.75,000/- from the contractors who have lumpsum deposit with the concerned Chief Engineers ie dispensed with and in lieu thereof. Bank Qugrantee or DD obtained in favour of tha officer as specified in the tendar, at the rate of 1% of the Estimate contract value will be oollected wihout any concession. The balance of EMD at the rate of 1.5% will be collected while concluding the agreement and tho Bank Guarantee shall be unconditional and irrevocable as par the standard format enclosed to the tender document. The contractors who have L.S. Deposit with concerned Chlaf Engineer will be permitted to take back their deposits, subjact to conditions that they are free from all liabilities.
3.01.9 Aplicabltlty of qualification criteria & EMD etc.,
The qualification creteria at para 3.02 aa well as modified procedure of collecting EMD in the shape of Bank Guarantee wilt not be made applicable for the works costing Rs.10 lakhs and below. For thase works costing Rs.10.00 lakhs and bellow single cover system shall be followed and the EMD ahall be submitted along with the completed Tender Schedule.
3.01.10 Subletting
The subletting of the works is strictly prohibited un-officially. In the event it is found that any portion of the work is sublet, action will be taken against the contractor by debarring him from participating in the tander for the period as decided by the Engineer-in-Chief/ Chief Engineer concerned. However, the debarring pariod shall not be less than one year.
Contd. Page.7.
Page.No.7
3.02. Qualification criteria
To qualify for award of the Contract, each bidder, in his/ her name should have, during the last five years (specified financial years i.e. they should be immediately preceding the financial year in which tenders are invited)
Satisfactorily completed not less than 90 percent of contract value as a prime contractor and similar works of value not less than Rs. @ (usually not less than 50% of estimated value of contract) in eny one year, during the tast 5 years.
Should hava executed in any one year, the following minimUm quantities of works.
Cement concrete including RCC and PSC
Cu. M
Earth work in both excavation and embankment
Cu. M
OHSRs
Nos and total capacity in liters
Pipeline laying, joiming & testing
Km
Filters Units
Ltrs
a) Rapid Sand Filters
b)Slow Sand Filter
Supply erection and testing of power pumps
K.W
(Relevant principle items be indicated)
(Usually 50 percent of the expected peak quantities of construction per year)
Each bidder should further demonstrate
Availability either owned or leased of the followlng key and critical equipment for the work
Road Rollers (8 to 10 T )
Water Tanker
Proclainers
Concrete Mixtures
Pipe Line hydraulic testing equipment
Equipment for BT work with cold Mix
Equipment for BT work with hot mix
Note (Based on the studies carried out by the Engtneer, true minimum suggested major equipment to obtain the completion of works in accordance with the presbribad construction schedule/ a mile stones are shown in the above list)
Availability of the Key personnel with adequate experience as required should be indicated based on the requiremennt for that work to be executed.
Liquid asetts/ credit facilities of not less than Rs.______________lakhs(credit lines letter of ered / solvency certificate from Banks etc., shall be equivevalent of the estimated cash flow for three months in peak
EMD in the shape of Bank Guarantee in the standard format enclosed, for Rs.(one percent of the estimated contract value) to be valid for the period as indicated at para (d) i.e. pariod of completion plus defect liability period.
Experience relating to the works executed in State/ Central Government departments or State/ Central Government undertaktngs shall only be considered.
3.02.3. Bid Capaciy
The sub contactors/ GPA holders experience shall not be taken into account in determining the bidders quallfying criteria. Tenderers who meet the requirement qualification cretaria will be quallfied only if their available bid capacity is more than the estimated contract value. Tha available bid capacity will be caliculated as under.
Assessed available bid capacity: 2AN-B Where A= Maximum value of civil engineering works executed in any one yaer dunng thę last five years (updated_______________________ price lavel) taking into account the completed as well as works in progress. N= Number of years prescribed for, completion of the works for which tenders are invited. If months are specified they shall be converted in to years B= Value of existing comitment and ongoing works to be completed during the period of completion of works for which tenders are invited
Note:-The statement showing the value of existing commitments and ongoing works as well the stipulated period of completion remaining for each of the works listed should be issued by the Engineer-in-Charge of Government department, not below the rank of Executive Engineer or equivalent and countersigned by Superintending Engineer or equivalent. The statement to the above effect shall be clearly enclosed to the Bidding Document, and the tenderer shall furnish the perticulars invariably in the same format failing which the tender shall be treated as incomplete and summarily be rejected.
@=-----------*price level. Financial turnover and cost of completed works of previous years shall be given weightage of 10 percent year to bring them to......Price level*. *The financial year in which bids are invited.
3.02.4
Even though the tenderer meets the above qualification critaria, he/she is subject be disqualified if he/she is found to have misled or made false representation in the forms, statements submitted in proof of the qualification requirements or records of poor performance such as abandoning works not properly completed in the contract, inordinate delays in completions, litigation history and or financia1 failures and or participated in the previoue tendering for the same works and had quoted unreasonably high bid prices. In addition to the above, even while execution of the work, if found that the Contractor had produced false/ fake certificates of experience, he/she will be blacklisted and work wiil be takan over invoking clauce 60(a) of PS to APSS.
3.02.5.
Tenders shall be valid for a period of 1/2/3 months as the case may be. Before the expiry of the validity, the authority competent to call for tenders shall seek for further extension of validity from the contractors and in caae the validity is not extanded his/ her tender will not be considered and the EMD shall be returned. During the period of validity, if any tenderer withdraws his tender, his/ her EMD shall be forfeited.
Contd. Page. 8.
Page.No.8
4.0. Evaluadon of Tenders
4.01. Receipt of Tenders
The Tender schedules snall be issued upto one day prior to the last day of submission of Tenders. Tho tankers shall be received at the oIace and Lima ae spe‹xfied in the Tender Notice. The contractor shall be allowed to 8ubmit the tender Either personally or through his agent or by post. In case of submission of tender by post the risk and responsibility for either loss or delays in transit of the earns is to be txxne by tie comrector. Tra tendar opening autnorify will not consioer any lender reserved by him after the expiry of date and tima fixed for receipt of tenders.
4.01.1 Tenders will be received in two parts in 2 different sealed covors. Cover-A and Cover-B. The Cover-A shall I contain qualification data Viz., Annual Turnover and value of works under execution etc.. as at para 3.02. The Cover-B will contain the financial bid for the work in question. The Covar-A and Cover-B will be sealed and kept in another sealed envelops (cover-C) supplied by the department while issuing Tender Schedules.
4.01.2. The Executive Engineers and Supertntending Engineers delegated with the power to invite tenders will open and evaluate the tenders as par the qualification Criteria. While opening the Tendars care should be taken to ffrst open Cover-C in the presence of the tenderers or their authorised reprasentatives and other officials concerned on the specified date and time and alao to verify whether the Covar-A and Cover-B are property saeaed and minutes be recorded to this effect then and there only. In case the Cowers A&B or any one of them are found unaealad, such tander will not be opened and summarily rejected.
4 01.3.First Cover (Covar-A) suparacribed as "TECHNICAL BID" containing the qualification data as described at para 3.02 will be opened.
4.01.4. Second Cover (Cover-B), superscribed as "PRICE BID" shall contain the Schedule-A i.e., the statement of description of work, quantity, estimate rate and amount. Price bid (cover-B) of those tenderers who aro determined as qualified as per eligibility criteria will be opened on the date specified in the tender notice and the Cover-B of un-quallfied Tnderer will not be oponed and kept in the safe custody till the tandars are finalised and there aftar shall be returned to them along with E.M.D. The schedule-A of pricc bid shall contain the working items indicated as part—I which are to be executed and L.S. Provisions as Part-II. The premium or discount quoted by the contractor shall be applicable only for part-I. Howevar, the provisions containad in part-II will be operable basing on the conditions provided in the tender schedules. The tenderers wilt have to state clearly their willingness to execute the work at percentage excass or less or at par over the Estimate Contract Value indicated at Part-I at the space provided therein.
4.01.5 Before recommending/ accepting the tender, the tender accepting authorify shall verrfy the corractness of certificates submitted to meet the eliglbility criteria and specifically for experiencc, the authanticated agreements or pravious works executed by the lowest tanderer, shall be called for.
The EMD wfll be returned to the qualified but unsuccessful tenderer either after finalisation of tenders or on expiry of validity of tendee which evor earlior
Contd. Page. 9.
Page.No.9
4.02. Finalisation of Tenders.
4.02.1. Tenders will be finalised by the departmental officers as indicated below:
S.No
Eest.Value of work put to tender (Rs.in lakhs)
Designation
Powers of acceptance of Tender.
1.
Upto Rs. 2.00
Dy. Executive Enginaer
Below or at Estimate rates
Executive Enginaer
Upto 5% of excess at over Estimate rates
Superintending Engineer
Above 5% upto 10% excess over Estimate rates.
Chief Enginneer / Enigneer-in-Chief
Above 10% upto 15% excess over estimate rates.
2.
Abaove Re. 2.00 to Re. 10.00 lakhs
Executive Enginaer
Upto 5% of excess at over Estimate rates
Superintending Engineer
Above 5% upto 10% excess over Estimate rates.
Chief Enginneer / Enigneer-in-Chief
Above 10% upto 15% excess over estimate rates.
3.
Above Re.10.00 to Re.50.00 lekhs
Superintending Engineer
Upto 10% excess over Estimate rates.
Chief Enginneer / Enigneer-in-Chief
Above 10% upto 15% excess over estimate rates.
4.
Above Rs.50.00 lakhs to Rs. 100.00 lakhs
Chief Enginaer/ Infgineer-in-Chief
Upto 15% of excess at over Estimate rates
5
Above above 100.00 lakhs
Tender Committee
Upto 15% excess over estimate rates
Note: In case of Mandal Parishad and Gram Panchayat works the Mandal Parihsad Development Officer and Grampanchayats resprectively are empowered to accept tenders on recommendation of above Enginees.
The existing tender committee constituted in G.O.Ms.No.589,PR &RD Dept dated 29.9.89 consisting of the following members shall continue for finalisation of tenders for works coating above Rs. 100.00 lakhs.
Prinñlpal Secretary to Government, Fin & Plg (Fin.Wing) or his nominee
4.02.2 The tendere for the works costing mora than Rs.1.00 crore will be referred to tender committee along with technical bid evaluation and price bid evaluation for consideration. The tender committee shall scrutinise the tendere submitted by Engineer-in-Chief/ Chief Engineer in accordance with tha conditions stipulated in the tender document and in case of any discrepancy or non-adherence to the conditions, the same shall be binding both on the tender deciding authority and the contractor. In case of any ambiguity the decision taken by the tender committee shall be final.
4.02.3. Negotiations are not permitted to be conducted at any level.
4.02.4. The time allowed from the date of publication of tender notices to the date of receipt of tenders is 14 days for the firat call and 7 days for the second call. The tenders will be recieved for works costing above 100.00 lakhs following three box system i.e. at SEs office, Office of the SP of the District where the SEs office located and one in the Office of the CE (concerned) or by post to the SE concerned.
4.02.5. Tender parcentage:
a) Maximum ceiling
The maximum permisible tender excess is reduced from existing 20% to 15% over the estimated contract value in partial modificaion of G.O.Ms.No.477, PR & RD Department, dt.12-11-98 and in case the excess is more than 15% the tenders shall be In sur«meri/y rejected. At the earno lime, lha tenders recalled with the maximum permissible percentage excesa are not necessarily to be accepted, they may be accepted basing on the trend of tenders accepted either in the project or in near vicinity for similar works. In case the trend of tender available relates to considerable time gap, the accepted premium of the tenders be updated with reference to the present prica index and with juatifiabla reasons only the lenders shall ba accopted.
b) Discount tenders (Percentage less than Estimated cost)
Tenders upto15% less than the estimate may be accepted but for tenders which are less by more that 15% of the estimate a bank guaratee or demand draft to the difference between the tendered amount and 85% of the estimate value should be taken at the time of Agreement so that if the tenderer leaves the works midway and the department is forced to call for tenderss for the work once atain, the bank guarantee or demand draft shall be used to inance the retendered work.
4.02.6. The tenders received if found to have abnormally high percentage or within the permissible ceiling limits prescribed but under collusion or due to unethical practices adopted at the time of tendering process shall be rejected.
5.0. Committees to resolve Inter-Departmental problems:
In order to expedite execution of works and to remove any dificulty that contractors may face in obtaining clearances and other infrastructure facilities from various departments such as shifting of power lines, procurement of blasting materials, power supply connection etc athe District level. the Collector will formulate Committees and take necessary steps. The Chief Secretary will have periodical review with the concerned Secretaries and Chief Engineers in order to resolve the difficulties which could not be sorted out at District level. The Heads of the Department are directed to constitute suitable committees at different levels for speedy settlement of the different kinds of or levels of disputes of technical nature by the Chief Engineers concerned.
Contd. Page. 10.
Page.No.10
ANNEXURE - II Annexure to G.O.Ma.No.195,PR & RD(Progs-II)Dept. dated 10th May, 1999
Government here by order to introduce an improved system of periodic monitoring and evaluatin of the performance and capabilities of contractors. The contractors who have already rigistered with the competent authorities for corresponding classes will continue to have the registration valid till the period indicated therein. However their class of registration is subject to evaluation of the performance as per the evaluation format appended, based on which they shall either be down graded or upgraded as per the credits obtained in the evaluation.
The evaluation will be done based on the following criteria.
Technical Qualification
Standing in Civil contract field relating to the specialisation for which the contractor submits the particulars either for registration or renewal or upgradation.
Records of execution of works.
Plant end machinery available with the contractor.
Financial status.
Training in National Academy of Construction (NAC)
Membership of BAI or any other professional bodies.
History of litigation.
The basis for the above criteria and procedure to furnish the details required therefore are discussed below
BASIS FOR EVALUATION CRITERIA
TECHNICAL QUALIFICATONS: Role of technical agents in execution of Civil engineering works is of quite significance more particularly in L.S. contracts. Keeping this in view this criterion is introduced and the credits are indicated for self-qualification of the contractor and quatification and experianca of the employed Engineers by the contractors. In addition suitable credits are alao assigned for the manpower possessed by the contractor who are trained in N.A.C.
STANDING IN CIVIL CONTRACT FIELD:- The experience of the contractor in the clvil contract field is considered as one of the important criterion in as much as the experienced contractor will have greater exposure to the working environment, procedure of execution of public works and also have quality consciousness. Considering the above aspects the total length of experience as well as the experience in the present class of contract are aasigned with suitable credits.
RECORD OF EXECUTION OF WORK: - In addition to the experience in execution of Civil Engineering works a contractor may possess experience in certain specialised fields such as Irrigation works, R&B works, watar supply and sanitary works etc. In casa a contactor files an application for either registration or renewal or upgradation in a particular field of specialisation, his record of execution of works should be assessed. Therefore in this criterion, credits have been assigned for executing similar nature of works during the last 5 years from the yaar in which the files applicatlon so as to evaluate to upto date knowledge of the work culture since the last five years bacause the contractor's registration is valid for a period of 5 years. Similarly credits ara also assigned for having completed the similar nature of works within the agreement period unless and other wise it is extended for the reasons beyond the control of the contractor. However if a contractor completes the works ahead of the agreement period additional waightage will be given by the sutable methodology indicated tharein.
PLANT AND M1CHtNERY:- It is expediant that a contractor should possess necessary plant and machinery of his own that are required to execute the nature of work for which his perfarmance is evaluated, in order to assess his capability of executing the works within the stipulated period. Hence suitable credits have bean aasigeed to this criterion, however the required plant and machlnary will be indicated for the different works by the concerned engineers who evaluate the performance.
FINANCIAL STATUS :- Since the Government have been implementing the works in various public works Department with huge outlays, it is necessary to asaess the financial capability of a contractor to commence the work and continue the work at least for a minimum period of 3 months without waiting for the bills to be paid by the concerned authorlties. The criterion has therefore been given importance and suitable credits are assigned for different components viz. annual average turnover, availability of liquidated assets such as solvancy / overdraft facility and other credit lines etc.
CONTRACTORS TRAINED IN NAC:- In case the contractor himself trained in the Natidnai Academy of Contruction it is expected that he will be able to possaes better skill in execution of work as wel as contract management, hence suitable creidits are assigned to this criterion.
MENBERSHIP IN BAI AND ANY OTHER PROFESSIONAL BODIES:-This critarion would raveal that the contractors access to interact or to have interface wiih differemt professional experts for up-dating his technical skills. Keeping this in view suitabe credits are assigned.
HISTORY LITIGATION:-This criterion is introduced to assesscharacter andd professional ethicsof a contractor. Various items have been identified under this criterion which are assigned suitable for each item. The sum total of credits achieved by a contractor for all the above seven criteria. It is imparative to mention that in case the concealment or misleading/ false information is furnished, the contractor shall face very severe action such as blacklisting or debarring from the contracting field. The contractor shall submit an affidavit to the effect that the history of litigation furnished by him s true and incase it is detected at any stage he will abide by the action taken the Government without approaching to any court whatsoever for redressal. Before taking action against the contractor the engineers will, after through probeand enquiry will give suitable opportunity to the for contractor for offering his explanation and then initiate action against him.
PROCEDURE TO FURNISH THE PARTICULARS FOR EACH OF THE ABOVE AVALUATION CRITERIA:
The contractors shall furninsh the informatin for each of the criterion (from i to vii)mentioned above ffollowing the formats supplied to them by the concerned engineers who evaluated their performance however the formats will broadly contain the particulars to be furnihed as stated below.
With regard to qualification, the copies of certifictes issued by the University / College / Polytechnic or any other competant authority shall be submitted.
The copies of registration right from the inception, to date shall be furnished.
Whith regard to ececution of works during the last 5 years the contractor shall produce the copies of the experience certificates issued by the competant authority not below the rank of Executive Engineer and counter-signed by the Superintending Engineer or equivalent indicating description of work, date of agreemnet, agreement value/ Revised agreement value date commencement, agreed date of completion, actual date of completion, total value of work done, reasons for delay if any, the physical quantities executed during each financial year etc.
The copies of the relevant document in prooff of possessing the equipment shall be produced.
The audited balance sheet, income tax returns for the past 5 years shall be submitted along with solvency. overdraft facility etc., in proof of the credit facility available to him.
The compies of certificate issued by the competent authority of NAC.
Copies of Membership of Builders Association or any professional body.
Note The copies of all the certificates documents shall invariabily be attested by a serving Executive Engineer of any works department of Government of Andhra Pradesh. For incorrectness of the copies of certificates / documents when compared with the Originals, action will be taken against E.E who attested the copies and the Contractor.
EVALUATION PROCEDURE
1. TECHNICAL QUALiFlOATION:
10
Contractor’s Qualification BE............3
Employed Engineers.
B.E with 4 years experience... . .......... 2 each
Diploma with 4 years experience 1.5 each
Trained Manpower from NAC Maximum of 1O credits
2. STANDING IN CIVIL CONTRACT FIELD
15
Experience from the lowest class upto the year of present class Registration (for each year 1 credit) Subject to a maximum of 5
Experience inthe present class from year registration to the present class to the of Evaluation (for each year 4 credits) Subject to maximum of 15.
">3. RECORD OF EXECUTION OF WORKS
25
(during preceding five year)
Similar Nature of works as prime contractor for each Rs. 2.00 cr. (2) credit and additional Rs. 1 cr in that year will fetch(1) credit. Cumulative of all for 5 years
Works completed with agreement period- each work of Rs.1 cr. will be given (1) credit maximuim of 25 credits
4. PLANT AND MACHINERY.
10
Requiring to the work of specialisation.
5. FINANCIAL STATUS.
25
Annual average-turn over during the preceding preceding five years.
For each Rs.1 crore. 2
For every additional Rs. 1 croree. 1 Subject to a maximum of 25 credits.
6. CONTRACTOR TRAINED IN NAC(CDI)
10
7. MENBERSHIP IN BAI AND ANY OTHER PROFESSIONAL BODIES
Tribal Welfare Department - Works programmes for the benefit of Scheduled Tribes – Allotment of works in Tribal Sub-Plan Areas and other Areas to the Local Village Development Committees (VDCs)/Mahile Sanghames/Societies/Ayacutdars / Beneficiaries – contain concessions – Sanctioned. ------------------------------------------------------------------------------------------------------------------------
SOCIAL WELFARE (V2) DEPARTMENT
G.O.MS .NO 30.
Dated 17th February, 1994.
Read the following :-
G.O Ms.No.25, Social welfare (V) Dept., dt 13-2-1986
G.OMS.NO 355, general administration (Ser.A) Dept., dt 11-5-1990
G.O.Ms.No.176, Irrigation & Command Area Development Dept., dt 3-6-1992
From the Commissioner of Tribal Welfare , Hyderabad Lr.No. DTW/L2/17621/92, dated 5-12-1992.
From the Commissioner of Tribal Welfare, Hyderabad. Lr.No.DTW/L2/17621/92, dated 29-3-1993
***
ORDER:
In the interest of speedy and quality execution of work and also to ensure the accrual of benefits to the local tribals themselves and to inculcate a sense of belonging through participatory approach, government have decided to entrust the execution of all Civil works benefiting the tribes in tribes in tribal area and other areas to village Development Committees/Mahila Sanghams / (Grama Abhivrudhi Sangam)/Societies comprising of the local tribals etc. on nomination basis irrespective of financial limit’s and depending on local initiative and discretion of the project officer, integrated Tribal Development Agency/District Collector concerned.
2. Considering that various civil works in the tribal areas are implemented by various Departments, Government have also decided that it is necessary to delegate certain powers to District Collectors/Project officers, Integrated Tribal Development Agencies in regard to according administrative/technical sanctions to the works relating to minor irrigation, Panchayat Raj and Tribal Welfare Departments executed Tribal areas.
3. The following delegation of powers is, therefore, ordered with immediate effect in as for as works in tribal areas are concerned.
Administrative Sanction:
Project officer, Integrated tribal Development Agency shall be competent to accord administrative sanction of all the works up to a limit of Rs 3.00 lakhs in the area of his jurisdiction;
District Collector concerned shall be competent to accord administrative sanction for all the works exceeding Rs. 3.00 lakhs in tribal area:
District Collector small be competent to accord sanction for all the works in the areas other than the Tribal Sub-Plan areas:
Technical Sanctions:
Executive Engineer concerned shall be competent to accord technical sanction to works up to Rs 5.00 lakh:
Superintending Engineer concerned shall be competent to accord sanction for all the works not exceeding Rs 25.00 lakhs:
The Chief Engineer shall be competent to accord technical sanction for the works above Rs 25.00 lakhs.
Delegation of powers for purchase of materials:
Integrated Tribal Development Agency:
The purchase/procurement of materials for the implementation of the works shall be made through a committee consisting of District Collector, Project officer, Integrated Tribal Development Agency and the Executive Engineers of the concerned departments except for those materials, purchases of which are centralised .
In the case of Lift Irrigation Schemes, the representatives of ayacutdars will also be involved in the purchase committees by co-option. The project officer, Integrated Tribal Development Agency concerned will be the Convener.
In non-Integrated tribal Development Agency areas the District Collector, shall nominate any other suitable officer as a convener.
3. Government have also decided that entrustment of works benefiting is the tribal in the tribal and other areas shall be essentially by nomination and the following powers for nomination are delegated:
The project officer, Integrated Tribal Development Agency/District Collector concerned shall take due decisions to interest to entrust the works depending on the initiative and interest to the local village Development Committees mahila Sanghams/ Societies Ayocutdars /beneficiaries, etc.
Priority in sanction of works is to be considered in favor of local tribals wherever they are willing to take up the work on their own.
The local Village Development Committees/Mahlla Sanghams /Societies Ayocutdars / beneficiaries, etc. of concerned scheduled Tribes shall be entrusted with the works irrespective of financial limits providing all the technical assistance and guidance necessary:
Exemption from collecting earnest money Deposit for the works taken up by them is made:
No solvency certificate need be insisted upon from them for the purpose of Registration.
4. The procedure as prescribed in the Annexure to this order shall be followed for execution of works. However, the Commissioner of Tribal Welfare/Director of Tribal Welfare, Hyderabad is authorized to issue such additional guidelines within the frame work of the Government orders as may be necessary from time to time to ensure smooth implementation of the Programme /works.
5. These orders are issued pending amendments/ relaxations to the Codes relevant to Minor Irrigation/Panchayat Raj works, However, this order will not apply to the works of Roads & Building and Major Irrigation Wing.
6. Withdrawal of sanction order of funds from the Joint Account etc., shall be vested with the project officers, Integrated Tribal Development Agencies in Integrated Tribal Development Agency Districts and the District Collectors in Non-Integrated Tribal Development Agency districts in case of any dispute or deviation of procedure after taking up of the work.
7. This order issues with the concurrence of Finance & Planning (Fin. Wing) Department vide their U.O.No 1645/44/Expr.PWD/94-1, dated: 2-2-1994.
(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)
T. MUNI VENKATAPPA
PRL. SECRETARY TO GOVERNMENT
To,
The Commissioner of Tribal Welfare, A.P., Hyderabad
The Chief Engineer (Tribal Welfare), Hyderabad.
All Project officers of Integrated Tribal Development Agencies.
All District Collectors.
Copy to :
Panchayat Raj & Rural Development Department.
Irrigation & Command Area Development Department.
Transport, Roads & Buildings Department.
Finance & Planning (Fin. Wing) Department.
All Superintending Engineers and Executive Engineers of Tribal Welfare though Chief Engineer (Tribal Welfare), Hyderabad
Managing Director, A.P Sch. Castes Coop. Finance Corpn.Ltd., Hyderabad.
Managing Director, A.P Sch. Tribes Coop. Finance Corpn.Ltd., Hyderabad
P.S to Prl Secretary to Government, Social Welfare Department.
P.S to Secretary to Government, Tribal Welfare
P.A to joint Secretary to Government S.W (Tribal Welfare ) Dept.
Social Welfare ‘SCP,II ’’E’ ‘D’ and ‘T’ Sections.
S.F./S.C
//Forwarded :: By order//
Sd/- SECTION OFFICER
A N N E X U R E
PROCEDURE FOR EXECUTION OF COMMUNITY ASSETS, LOCAL VILLAGE DEVELOPMENT COMMITTEES /MAHILA SANGHAMS ETC
BY PARTICIPATOR/MANAGEMENT
ORGANISATION OF VILLAGE DEVELOPMENT COMMITTEES: Basing on the experience so far in involving the village community in planning execution, maintenance and management of works like buildings, minor irrigation schemes etc., the Assistant Engineer concerned with the assistance of staff / Non-Government organisations identified by the project officers /Sub-collector etc., will motivate the villagers by organizing visits to such Villages /works. The Villagers / Ayacutdars / Mahila Mandali of that village, as case may be, will be organized into a village Development Committee (V.D.C) The village Development Committee will select and amongs them as their representative to be the joint account holder.
The Assistance Engineer shall conduct a training class in the Village for men and women to give exposure on various technical on various technical details of the proposed work. The Assistant Engineer will furnish a copy of the cross-sectional diagram and suitably explain the scheme (If minor irrigation scheme) to the community/Village development Committee. The Assistant Engineer and work inspector shall take responsibility to give necessary training and guidance in all items of work, Viz., earth work excavation, collection of metal of specified sizes, construction of masonry/ walls curing etc, this shall also pick up two on throe tribes and attach them to the skilled masons, rod benders, carpentry etc., for training the Village Development Committees, may be supplied with required tools at the beginning of the training.
The Village development Committee shall be consulted in the identification of site and nature of Minor Irrigation Schemes.
A separate note book shall be maintained by Village Development Committee, Mahila Sangham etc., for all the details of work viz., items like sand, iron, metal, cement, their unit rates and quantities etc. This shall be written in the local language by the literate member, as nominated by the Community.
Normally, it is found that the tribes working on podu not have suitable implements for carrying out the construction works. The Assistant Engineer shall assess in consultation with the local tribals and provide needed implements like spade gamala, crowbar, hammer etc., through the woman’s group,/Village Development Committee form tools and plants provision.
The Executive Engineer/Assistant Engineer shall be responsible to supply estimated quantity of cement/ steel for the work at site preferably in bulk or from time to time as decided by the project officer/District Collector the entries of which will be made by the nominee or Village Development Committee in the note book of Village Development Committee /Mahila Sangham etc., from time to time with a view to keep the entire transactions in the knowledge of Mahila Sang ham Members/Village Development committee Members.
As far as possible , work inspector shall be positioned close to work sites preferably at the rate of one person for cluster of villages (Contiguous)with a view to ensuring frequent visits and rendering guidance to tribals in all respects of the execution of works programme.
The Assistant Engineer shall cause open a special savings Bank Account with nearby branch of Commercial / Cooperative / Rural Banks in the name of village, Development Committee etc., and funds pertaining to the Labour component or any other material like sand etc., may be deposited in instalments. The Special Savings Bank Account money may be treated as imprest amount.
The Bank Account shall be operated under tie joint signatory of the/ Assistant Engineer and the representative of Village Development Committee /Mahila Sangham etc, It shall be ensured that the tribes receive payments one day before the shandy day facilitating them to buy their provisions/ requirements in the weekly shandy and actively participate in spendy execution of work.
The Assistant Engineer shall also record the value of work done atleast on weekly basis and arrange payments.
The deputy Executive Engineer shall inspect the sand quarries and ensure quality of sand for use at site. Work Inspectors shall certify the quality of work in their visits from time to time. The Deputy Executive Engineer shall also inspect the works thoroughly to ensure the quality of work executed.
During the course on execution, the Assistant Engineer shall appreciate the modification suggested of the tribal for any changes proposed for utmost utility of the structures, He is, therefore requested to incorporate such modifications with the prior approval of District Collector/ project Officer, Integrated Tribal Development Agency.
Executive Engineer shall ensure that the works are completed within the time schedule and the assists created are durable.
The Engineering Division shall adopt special rates of wages in the S.S.R. provided for construction works in the hilly and interior tracts wherever applicable.
During the course of construction, the members of the Village Development Committee women group etc., may be constantly motivated to save part of their wages towards thrift fund from their own wage component.
Steel and cement required for the work shall be supplied Departmentally only. There should be close monitoring and also quality control check/ verification of works executed by Executive Engineer /officers nominated by District Collector/Project Officer , Integrated Tribal Development Agency.
After Completion of work, N.M.R vouchers, bills, paid vouchers and all the connected records including M. books shall be hands over to Executive Engineers Officer at integrated tribal Development Agency Headquarters and for Non-Integrated Tribal Development Agency districts to Executive Engineer Concerned.
The Work Inspector at site, shall write his diary and it shall be checked by the Deputy Executive Engineer from time to time.
All necessary steps to ensure that quality of works are maintained shall be taken by the engineering/Technical Staff/ District Collector/ Project Officer, Integrated Tribal Development Agency. Apart from imparting necessary training to the members, the and for taking up curing, proper consolidation of tank bund and such other measures would also be exclaimed to them to enable them to appreciate the need for same.
On completion of the work, the Committee (in case of Minor Irrigation schemes) will be given training on day to day maintenance of the scheme such that their dependence, on the Government for such maintenance is minimized to the extent possible, Such other Steps shall be taken to ensure that the funds are spent properly to yield best possible results for which intensive monitoring, frequent visits by all supervisory officers including Project Officers of Integrated Tribal Welfare, officer etc., shall be undertaken.
After completion of work understood, Project Officer, integrated Tribal Development Agency /Collector may allocate 50% of the unspent balances, if any, to the Committee/ Sangham which executed the work to be matched with contribution by beneficiaries, 50% of such savings will be deposited in the joint account to be used towards maintenance or repairs of the structure/ assets so created and the balance 50% of unutilized funds may be spent for other such other communiy requirements, etc., as the Village Development Committee or sangham etc., may decide.
In case any demand is made by Village Development Committee etc., for revision of estimates etc., Collector/Project Officer Integrated Tribal Development Agency may utilize the services of Government recognized Engineering Agency or University Engineering wings for preparation of Revised Estimates/check measurement etc.
The interest , if any, accrued on those grants deposited by Integrated Tribal Development Agency/District Collector in the Bank should be remitted back to the Project Officer, Integrated Tribal Development Agency/District Collector, what in turn can allocate as para 21.
The type design estimate sanction proceeding etc., approved has to be provided to the Village Development Committee/Mahila Sang ham etc., concerned.
Supply of quality material and ensuring quality is the responsibility of the Engineering/technical department entirely.
The members of the Village Development Committee/Mahila Sangham/ Ayacutdars Committee .etc., are to be involved in the purchase of material component in case of lift Irrigation Schemes.
Since the procedure envisages constant technical guidance and skilled training where necessary etc., the Engineering staff to be entrusted with such works should be selectively identified/posted and duly motivated.
The ensure proper implementation of the programmes, the District Collector/ Project Officer, Integrated Tribal Development Agency may involve the Revenue Divisional Officer/ Sub-Collector or any other officer for monitoring /review etc., as may be demand necessary at the various stages of the implementation.